WCRR July Interactive Map
Forebay Construction July 2020 Forebay Construction July 2020 Stormline Installation July 2020 Stormline Installation July 2020 Piling Abutments July 2020 Abutment Piles Complete July 2020 Forming Bridge Deck July 2020 Earthworks For Future Road July 2020 Retaining Wall Concrete Poured July 2020 Progress on Grading and Geogrid July 2020 Excavation for Bridge Abutment July 2020 Centre Pier Construction July 2020 Centre Pier Construction July 2020

Forebay Construction July 2020

Sediment forebays are located at each major inlet to trap sediment and preserve the capacity of the main pond.

Forebay Construction July 2020

Sediment forebays are located at each major inlet to trap sediment and preserve the capacity of the main pond.

Stormline Installation July 2020

Installing a stormline between the bridges.

Stormline Installation July 2020

Installing a stormline between the bridges.

Piling Abutments July 2020

The piles are marked for length to determine the depth driven and verify the number of blows on the pile driver.

Abutment Piles Complete July 2020

Looking south at the piles for the north and south bridge abutments

Forming Bridge Deck July 2020

Once the girders are installed it takes several weeks to form the bridge deck

Earthworks For Future Road July 2020

Crews excavate and grade the future 109 Street SW

Retaining Wall Concrete Poured July 2020

The concrete for a portion of the retaining wall next to Valley Ridge Heights NW is poured with the mountain motif.

Progress on Grading and Geogrid July 2020

Excavation for Bridge Abutment July 2020

Looking north with the Trans-Canada Highway visible in the background

Centre Pier Construction July 2020

Forming centre pier

Centre Pier Construction July 2020