Bow River Bridge – A Look Back at 2022
January 10, 2023
A Look Back at the Bow River Bridge in 2022
Work continued on the Bow River Bridge project, with significant milestones such as the new bridge over Scenic Acres Link N.W. opening to traffic and pouring the last cast-in-place bridge segment.
By the Numbers
To date, there have been approximately 21,000 cubic metres of concrete placed on the West Bow River Bridge project, including over 4,900 cubic metres that were placed in 2022.
More than 640,00 kilograms of reinforcing steel (rebar) was placed in 2022, with a total of 3.2 million kilograms having been placed on the project since it started.
The new bridge over Scenic Acres Link N.W., shown in red, opened to traffic in 2022