Project Update – October 25, 2021
What’s Happening in Traffic This Week
Crestmont Boulevard S.W. Fully Closed for 15 Minutes
Tomorrow, October 26, Crestmont Boulevard S.W. will be fully closed for approximately 15 minutes between 10 a.m. and 11 a.m. to install an electrical pole.
Traffic Stoppages on 17 Avenue S.W. East of 101 Street S.W.
On Tuesday, October 26, from 1 p.m. until 3 p.m. and Wednesday, October 27, from 9 a.m. until 11 a.m. there will multiple traffic stoppages on 17 Avenue S.W. east of 101 Street S.W. to allow for ENMAX utility work. Each stoppage is expected to last approximately five minutes.
Traffic delays are expected. Please plan accordingly.
Single Lane of Alternating Traffic on 17 Avenue S.W. West of 101 Street S.W.
From 9 a.m. to 3 p.m. on Tuesday, October 26, 17 Avenue S.W. will operate as a single lane of alternating traffic between 101 Street S.W. and Lower Springbank Road for utility work.
Intermittent Traffic Stoppages on Highway 8
On Wednesday, October 27, between 9:30 a.m. and 3:30 p.m., there will be intermittent traffic stoppages on Highway 8 west of 69 Street S.W. for utility work.
Lane Closures on 17 Avenue S.W. – Slopeview Drive to St. Moritz Drive S.W.
Utility work will be ongoing along 17 Avenue S.W. until the end of the month. Please drive cautiously and expect delays.
Westbound Trans-Canada Highway to Northbound Stoney Trail Ramp
The ramp from westbound Trans-Canada Highway to northbound Stoney Trail will be reduced to one lane until the end of the week.
All work is weather dependent. Please check 511 Alberta and The City of Calgary’s traffic information map for up-to-date information on traffic detours and speed reductions.
We appreciate your patience during construction.

Segmental Bridge Construction
Like stationary wooden forms that are used to shape concrete for bridge abutments, curbs and retaining walls (to name a few), form travellers are pre-assembled forms used to construct segmental bridges.
Segmental bridges, like this one, are constructed using many shorter segments whereas a more traditional bridge is constructed in large segments using girders.
Segmental bridges are often used when long spans are required or when access to the site is limited.

Trans-Canada Highway Improvements
Now that westbound Trans-Canada Highway traffic has been shifted to the new lanes, work on the future eastbound lanes is underway.
Looking west at road construction for Trans-Canada Highway improvements The road in this section will be lowered approximately eight metres below the original elevation; the detour road shown on the left is lower than the original elevation and the new lanes shown on the right are at the new elevation This section of road is being raised approximately seven metres Looking west at the eastbound lanes under construction

Deck Pour Preparation
The truss screed – named because of its triangular shape – is installed, signaling the bridge deck is ready for concrete.
Screeding is the process of flattening and smoothing wet concrete. The truss screed is mounted on rails on either side of the bridge deck, and a screed attachment will be suspended from the truss allowing it to move back and forth to level and finish the concrete.
Bow Trail S.W.
This aerial photo shows the magnitude of the site and the depth of the ravine being filled to connect Bow Trail S.W. with 101 Street S.W. to the west.