Project Update – August 10, 2020
For up-to-date information on traffic detours and speed reductions, please visit 511 Alberta.
We appreciate your patience during construction.

Bridge Pier Construction
Looking south at the piers on the north side of the river
Southbound Stoney Trail Overnight Lane Closures
Until August 21, 2020, please expect overnight lane closures on southbound Stoney Trail from Scenic Acres Link N.W. to Nose Hill Drive N.W. Crews will be paving the new collector distributor road and on- and off-ramps between 7 pm and 6:30 am.
This work is weather dependent. Please check Alberta 511 for up-to-date traffic information.
Successful Bridge Deck Pour
Last week the third concrete bridge deck was poured. Thanks to residents on Valley Brook Circle N.W. and Valley Meadow Close N.W. for your patience during this overnight work.
Looking west at the bridge deck ready for concrete Truss screed ready for action Crews moisten and smooth the concrete by hand
Stormpond Complete East of Valley Ridge
Construction for the stormpond just east of Valley Brook Circle N.W. is complete. In the coming weeks crews will begin landscaping the area with native grasses.
July 23, 2020 – Placing topsoil along the interior slope of Pond 5 July 28, 2020 – Topsoil placement continues along the interior slope Large rock called rip rap is placed around the inlet and outlet pipes Rip rap is also placed in the forebay August 4, 2020 – Ready for landscaping
Valley Ridge Boulevard N.W. Roundabout
Controlled Blasting
One of the last masses of bedrock remaining on the Paskapoo Slope last weekThe same mass of bedrock as above this week
The Big Picture
Looking north from Crestmont at the future Valley Ridge Blvd NW alignment

Gravel Removal Complete
The gravel removal south of Old Banff Coach Road S.W., just west of West Springs, is complete.
Looking south at the gravel removal area
Watermain Installation Near Old Banff Coach Road S.W.
Construction to relocate a City of Calgary watermain continues.
Watermain construction just north of Old Banff Coach Road S.W. Example of a thrust block (image courtesy of waterhelp.org)
The water moving through the pipe down this steep slope will speed up (increased velocity) and cause thrust (a propulsive force). The force of thrust on the pipe can cause the pipe to move and possibly even pull apart, so thrust blocks are used to anchor the pipe and transfer the thrust force to the surrounding soil.
Geotechnical Surveys
Geotechnical work started last week and will continue for several weeks.
Drilling a geotechnical hole near Bow Trail S.W. to analyze ground conditions