Entries by Lindsay

Project Update – April 19, 2021

What’s Happening in Traffic This Week Westbound Trans-Canada Highway Ramp to Northbound Stoney Trail Until April 30, the ramp from westbound Trans-Canada Highway to northbound Stoney Trail will be reduced to one lane. Ramp speeds will be posted at 60 km/h. This is required for open-trench underground culvert construction.  All work is weather dependent. Please […]

Pile Driving at Bow Trail S.W.

Pile driving for the Bow Trail S.W. interchange is anticipated to start this week and continue for approximately one month (mid-May). Pile driving involves a pneumatic (air) hammer striking steel piles, which creates a repetitive pinging or hammering sound. Residents can expect increased noise and some vibration, which are expected to be minor and cease […]

Project Update – April 12, 2021

What’s Happening in Traffic This Week Trans-Canada Highway Reduced to One Lane Nightly Every night this week (until Friday, April 16) from 10 p.m. to 5 a.m., the Trans-Canada Highway will be reduced to a single lane in each direction at the Stoney Trail interchange. The lane closures are needed to install overhang brackets on […]

Project Update – April 5, 2021

What’s Happening in Traffic This Week Trans-Canada Highway Reduced to One Lane Nightly Every night from 10 p.m. to 5 a.m., April 11 to 16, the Trans-Canada Highway will be reduced to a single lane in each direction at the Stoney Trail interchange. The lane closures are needed for bridge overhang bracket installation. Delays are […]

Project Update – March 29, 2021

What’s Happening in Traffic This Week Westbound Trans-Canada Highway Shifting to Detour Please expect continued delays this week as final preparations on the Trans-Canada Highway detour (between Old Banff Coach Road and Valley Ridge Boulevard N.W.) are completed. The westbound lanes are expected to be shifted onto the detour early next week. All work is […]

UPDATED: Stockpile Next to Aspen Woods

Earthworks for the Bow Trail S.W. interchange continue this spring. Beginning the week of March 29, 2021, more topsoil will be stockpiled within the Transportation Utility Corridor (TUC) along the northwestern boundary of Aspen Woods. This work will continue as weather conditions permit and until excavation is complete. Over the course of the project, numerous […]