WCRR Interactive Map v2
Forebay Construction July 2020 Forebay Construction July 2020 Bridge Girders Installed September 2020 Piling Abutments August 2020 Abutment Piles Complete July 2020 Pouring Abutment Walls September 2020 Earthworks For Future Road July 2020 Retaining Wall Concrete Poured July 2020 Progress on Grading and Geogrid July 2020 Centre Piers Complete September 2020 Centre Pier Construction July 2020 Forming Centre Pier Cap October 2020 Bridge Deck Cured August 2020 Bridge Deck Poured August 2020 New Roundabout Completed September 2020 Placing Clay Liner September 2020 Bridge Girders October 2020 Girders Installed September 2020 Forming the Bridge Deck September 2020 Piling Abutments October 2020

Forebay Construction July 2020

Sediment forebays are located at each major inlet to trap sediment and preserve the capacity of the main pond.

Forebay Construction July 2020

Sediment forebays are located at each major inlet to trap sediment and preserve the capacity of the main pond.

Bridge Girders Installed September 2020

Looking east at the largest girders on the North Project – these girders are up to 54 metres long and 2.8 metres tall, which makes them a little longer than an Olympic swimming pool (50 metres).

Piling Abutments August 2020

Piles for the west and east abutments have been installed

Abutment Piles Complete July 2020

Looking south at the piles for the north and south bridge abutments

Pouring Abutment Walls September 2020

Earthworks For Future Road July 2020

Crews excavate and grade the future 109 Street SW

Retaining Wall Concrete Poured July 2020

The concrete for a portion of the retaining wall next to Valley Ridge Heights NW is poured with the mountain motif.

Progress on Grading and Geogrid July 2020

Centre Piers Complete September 2020

Looking north at centre pier construction.

Centre Pier Construction July 2020

Forming centre pier

Forming Centre Pier Cap October 2020

Looking west at the formwork for the centre pier cap

Bridge Deck Cured August 2020

This bridge deck was poured in July and the concrete has cured

Bridge Deck Poured August 2020

New Roundabout Completed September 2020

Looking north at the new roundabout

Placing Clay Liner September 2020

The clay lining allows the wet pond to contain and settle stormwater, returning cleaner water to rivers and streams

Bridge Girders October 2020

Looking up at support braces between girders

Girders Installed September 2020

Looking southeast at the bridge girders installed over the ramp from eastbound Trans-Canada to northbound Stoney Trail and over the future 1 Ave. S.W.

Forming the Bridge Deck September 2020

Looking southeast at the bridge girders installed over the ramp from eastbound Trans-Canada to northbound Stoney Trail and over the future 1 Ave. S.W.

Piling Abutments October 2020

Looking north at pile installations for the bridge abutments