Project Update – December 13, 2021
Super Structure Progress
The cast-in-place pier segments forming the bridge super structure are complete on the north side of the river.
On the south side of the river, both bridge piers are complete and work on the super structure is underway.
Underground Utilities
Building a major infrastructure project involves coordination with multiple utilities to relocate their existing infrastructure out of the highway right-of-way so that future access will have minimal impact on highway traffic.
Here’s a look at a few of the underground utilities in the South project area.
17 Avenue S.W. Interchange
The girders for the 17 Avenue S.W. bridge are in place and work on the deck is underway.