Stockpile Next to Aspen Woods

Earthworks for the Bow Trail S.W. interchange are underway. Crews will be using bulldozers, scrapers and backhoes to remove topsoil as part of grading the area for the future road. The topsoil will be temporarily stockpiled along the northwestern boundary of Aspen Woods for future use.

During topsoil removal and stockpiling, adjacent residents may find construction equipment coming close to their homes. While at times disruptive, this will be temporary and confined to the TUC. 

This work will continue for approximately two weeks before stopping for winter, and then resume again next spring when the weather turns favourable for earthworks. The stockpile is anticipated to be approximately six metres tall and about 10 metres from adjacent properties.